17.07.2019

Road marking at Section 7

Works are underway at M11 Highway’s Section 7.

In early July, Two Capitals Highway launched traffic through the M11 overpass on the regional road between Ushaki and Rublevo rural settlements. In the near future, overpasses on R41 (Lyuban - Luga) and 41K170 (Pogi-Novolisino) roads will start operating as well.

By 24 July, all works on laying asphalt concrete should be completed. By the same date, lighting systems will be fully installed. In the meantime, road-marking works have already started at ready sections, and lighting is already in place at km 580 to 610.

Since 17 July, testing of engineering systems has been underway at the central control center near the A-120 motor road.

 